Renewables.digital currently lists 14 renewable energy transactions in Australia between February 2026 and October 2026, with a combined capacity of 4,660 MW. By technology: Battery Storage (BESS) (10), Solar PV (6) and Onshore Wind (5). The most active companies are Atmos Renewables (3), BayWa r.e. (3), Copenhagen Infrastructure Partners (2) and Enervest (2). The most recent deal is “Atmos Renewables Acquires 262 MW Bullawah Wind Farm Development in NSW Riverina from BayWa r.e.” (16 October 2026).
14Transactions
4,660 MWTotal capacity
3Technologies
6With PPA
February 2026 – October 2026Period
Key facts
14 transactions between February 2026 and October 2026, 4,660 MW in total (average 333 MW per deal)
How many renewable energy transactions in Australia are listed?
Renewables.digital currently lists 14 renewable energy transactions in Australia between February 2026 and October 2026, with a combined capacity of 4,660 MW.
Who are the most active buyers of renewable energy in Australia?
Atmos Renewables (3), Palisade Investment Partners (2) and BW ESS (1) (number of deals).
Who are the most active sellers?
BayWa r.e. (3), ACEnergy (1) and Ark Energy (1) (number of deals).
What is the largest of the renewable energy transactions in Australia?
Octopus Australia Acquires 1.2 GW Hanworth BESS and Dunmore Solar & Battery Projects with 1,350 MW (4 February 2026).
Atmos Renewables has acquired the Bullawah Wind Farm development in the Riverina region of New South Wales from BayWa r.e. The Stage 2 component has 262 MW of South West REZ access rights, forming part of an overall 800 MW wind and 359 MW BESS project design. Investment readiness is targeted for 2027.
Atmos Renewables has acquired the 20 MWp Hughenden Solar Farm in central Queensland from BayWa r.e. Operational since 2018, the project has over 60,000 solar panels and is backed by a PPA with CS Energy.
Atmos Renewables has acquired the 106 MWp Yatpool Solar Farm in north-west Victoria from BayWa r.e. The operational project has approximately 350,000 solar panels and is backed by an offtake arrangement with Flow Power. It is located close to Atmos' existing Karadoc Solar Farm.
LGI Limited has acquired two fully operational NEM-connected solar farms in Queensland — Brigalow (27.3 MW) and Chinchilla (14.7 MW) — from IIG Solar Asset Trust for A$22 million. Both sites offer BESS co-location optionality and will be integrated with LGI's DACS system. The acquisition upgrades LGI's strategic pipeline target to over 120 MW.
Palisade Investment Partners has acquired, through Intera Renewables, two development-stage renewable energy projects in Australia: Monogorilby (up to 600 MW wind + 400 MWac / 1,600 MWh BESS in Queensland) from LP Renewable Projects, and Winton WRESST (400 MWac / 1,600 MWh grid-forming BESS in Victoria) from Celero Infrastructure. Both projects were acquired partway through development.
Copenhagen Infrastructure Partners (CI V) has acquired the Gawara Baya hybrid project in North Queensland, Australia from Windlab, comprising a 408 MW onshore wind farm and 104 MW of grid-forming BESS. Financial close secured with an AUD 1.7 billion facility from 10 banks. Construction is now underway with full operation expected in 2030.
BW ESS has acquired the 250 MW / 1,000 MWh Yanco BESS project in Riverina, New South Wales from ACEnergy. The ready-to-build project connects to the Yanco 132 kV substation with CATL as System Integrator and ACLE Services as BoP contractor. Construction commences later in 2026, with commercial operation planned for 2028, underpinned by a long-term capacity swap.
Vestas Development A/S has acquired the St Patricks Plains Wind Farm project in the Central Highlands of Tasmania, Australia from Ark Energy. Vestas is progressing through consent conditions, geotechnical engineering and detailed design ahead of construction. Ark Energy developed the project over approximately eight years through planning and approvals.
Enervest has acquired the 300 MW Northern Border Battery, a large-scale BESS project in development on the NSW–QLD border, connecting to the Dumaresq substation. The project is the first asset retained under Enervest's own-and-operate model and is expected to begin construction in early 2028, supporting grid reliability ahead of the closure of the Eraring coal power station in 2029.
CleanPeak Energy Holdings has signed an agreement to acquire 100% of Sustainable Energy Infrastructure (SEI), one of Australia's largest owners of sub-5 MW distributed solar and battery assets. SEI operates 71 MWac of solar PV across 16 sites and 42 MW of BESS across 11 sites in NSW, Victoria and South Australia. The acquisition accelerates CleanPeak's national renewable energy growth strategy.
Palisade Investment Partners has agreed to acquire a 100% interest in the 240 MWac / 960 MWh Summerfield BESS in South Australia from Copenhagen Infrastructure Partners, through its Australian renewable energy platform Intera Renewables. The project is currently under construction and is expected to reach commercial operation in late 2026, underpinned by a long-term tolling agreement with Origin Energy.
Iberdrola has completed the acquisition of the 242MW Ararat Wind Farm in Victoria, Australia, from Partners Group and OPTrust. Operational since 2017, it is Iberdrola's largest wind farm in Australia and its first owned generation asset in Victoria. The deal expands Iberdrola's presence to five Australian states and is backed by long-term PPAs. The company plans to invest €1 billion in Australia by 2028.
Flow Power has acquired the Dunedoo Energy Project, a 55 MW solar farm and 60 MW BESS located near Dunedoo in the Warrumbungle Shire, New South Wales, from ib vogt GmbH. The project holds State Significant Development approval and construction is scheduled to commence in 2026. Once operational, it will power up to 20,000 homes and businesses and provide grid stability services across regional NSW.
Octopus Australia has acquired the Hanworth Battery Energy Storage System in New South Wales and the Dunmore Solar and Battery project in Queensland. The acquisitions include a planned 1.2 GW / 4.8 GWh battery, set to become Australia’s largest, and a 300 MW solar project paired with 150 MW of battery storage.
Data as of 12 November 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.