Enervest appears in 1 renewable energy transaction tracked by Renewables.digital (1 as buyer) in May 2026, with a combined capacity of 300 MW. Technologies: Battery Storage (BESS) (1). Countries: Australia (1). The most recent deal is “Enervest Acquires 300 MW Northern Border Battery BESS Project on NSW–QLD Border” (18 May 2026).
Enervest has acquired the 300 MW Northern Border Battery, a large-scale BESS project in development on the NSW–QLD border, connecting to the Dumaresq substation. The project is the first asset retained under Enervest's own-and-operate model and is expected to begin construction in early 2028, supporting grid reliability ahead of the closure of the Eraring coal power station in 2029.
Data as of 30 September 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.