ACEnergy appears in 1 renewable energy transaction tracked by Renewables.digital (1 as seller) in August 2026, with a combined capacity of 250 MW. Technologies: Battery Storage (BESS) (1). Countries: Australia (1). The most recent deal is “BW ESS Acquires 250 MW / 1,000 MWh Yanco BESS in Riverina, New South Wales from ACEnergy” (13 August 2026).
BW ESS has acquired the 250 MW / 1,000 MWh Yanco BESS project in Riverina, New South Wales from ACEnergy. The ready-to-build project connects to the Yanco 132 kV substation with CATL as System Integrator and ACLE Services as BoP contractor. Construction commences later in 2026, with commercial operation planned for 2028, underpinned by a long-term capacity swap.
Data as of 30 September 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.