Hexicon Acquires 100% of Mareld Floating Offshore Wind Project in Sweden from Mainstream Renewable Power

Hexicon AB has agreed to acquire the remaining 50% stake in Mareld Green Energy AB from Mainstream Renewable Power, becoming sole owner of the Mareld floating offshore wind project in Western Sweden. With potential annual generation of up to 12 TWh, Mareld is one of Sweden's largest prospective offshore wind projects. A government decision on the SEZ permit is pending.

Transaction date: · Source: hexicongroup.com

Key facts

Transaction date
Technology
Offshore Wind
Transaction price
4.5 million (currency as reported in the source)
Country
Sweden
Region
Western Sweden
Location
Swedish Economic Zone, Western Sweden (offshore)
Continent
Europe
Development status
Under Development
PPA
n.a.

Technology details

Floating offshore wind project with the potential to generate up to 12 TWh of electricity annually, equivalent to the consumption of approximately 2 million households. Project is in the permitting phase; application under the Swedish Economic Zone Act (SEZ) was recommended for approval by the County Administrative Board of Västra Götaland in June 2024. Final government decision pending. Capacity in MW not disclosed.

Additional information

Hexicon acquires the remaining 50% stake for an upfront consideration of SEK 1 plus a milestone-based contingent consideration of EUR 4.5 million, payable if the project is awarded an offtake contract in a future auction. Hexicon now holds 100% of Mareld Green Energy AB. Hexicon is a floating wind developer and technology provider with a patented TwinWind™ design, listed on Nasdaq First North Market (ticker: HEXI).

Source

Original announcement: https://www.hexicongroup.com/single?slug=hexicon-ab-publ-acquires-the-remaining-shares-in-mareld-green-energy-ab-and-becomes-sole-owner

Related transactions

Explore more