Royal Vopak appears in 1 renewable energy transaction tracked by Renewables.digital (1 as buyer) in July 2026, with a combined capacity of 200 MW. Technologies: Battery Storage (BESS) (1). Countries: Netherlands (1). The most recent deal is “Royal Vopak Acquires 79% Stake in Green Energy Storage and Takes FID on 200 MW / 800 MWh BESS in Oosterhout, Netherlands” (2 July 2026).
Royal Vopak has completed the acquisition of a 79% controlling stake in Green Energy Storage (GES) and taken a final investment decision on a 200 MW / 800 MWh battery energy storage project in Oosterhout, Netherlands, for a total investment of approximately €230 million. Construction is set to begin shortly, with commercial operations expected in H1 2028. Greenchoice will offtake 50% of capacity under an 8-year tolling agreement.
Data as of 30 September 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.