R.Power appears in 1 renewable energy transaction tracked by Renewables.digital (1 as seller) in June 2026, with a combined capacity of 250 MW. Technologies: Battery Storage (BESS) (1). Countries: Poland (1). The most recent deal is “ENGIE Zielona Energia Acquires 250 MW / 1,000 MWh Tursko Wielki BESS Project in Poland from R.Power” (27 June 2026).
ENGIE Zielona Energia has acquired the special purpose vehicle developing the Tursko Wielki battery storage project in Świętokrzyskie Voivodeship, Poland, from R.Power. The 250 MW / 1,000 MWh project has reached ready-to-build status and will connect directly to the Połaniec power station. Construction is expected to begin in early 2027, with commissioning targeted for Q4 2028.
Data as of 30 September 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.