OX2 Sells 77 MW Urleasca Ready-to-Build Wind Farm in Romania to Scatec ASA
OX2 has completed the sale of the 77 MW Urleasca wind farm in south-east Romania to Scatec ASA. The ready-to-build project features 11 Nordex N175 turbines, holds a 15-year CfD with the Romanian State and is expected to generate approximately 244 GWh annually. Construction is scheduled to begin in Q3 2026 with commissioning planned for H2 2028.
Transaction date: · Source: ox2.com
Key facts
- Transaction date
- Technology
- Onshore Wind
- Capacity
- 77 MW
- Transaction price
- Not disclosed
- Buyer
- Scatec ASA
- Seller
- OX2
- Country
- Romania
- Region
- South-East Romania
- Location
- Urleasca, South-East Romania
- Continent
- Europe
- Development status
- Ready-to-Build
- PPA
- Yes
Technology details
11 Nordex N175/6.X MW wind turbines with a total capacity of 77 MW. Grid connectivity secured through a connection agreement with Romanian TSO Transelectrica. Construction scheduled to commence in Q3 2026, with commissioning planned for H2 2028. OX2 contracted to oversee the entire construction phase. Expected annual generation of approximately 244 GWh, sufficient to power 71,000 households, avoiding approximately 101,000 tonnes of CO₂-equivalent per year.
Power purchase agreement (PPA)
Long-term Contract-for-Difference (CfD) with the Romanian State, secured in 2025 for 43 MW of the project's installed capacity over a 15-year term.
Additional information
This is OX2's third Romanian transaction. OX2 has a 1.5 GW development and construction portfolio in Romania. In 2025, OX2 secured a 15-year CfD with the Romanian State for 43 MW of the project's installed capacity.