SMA Altenso appears in 1 renewable energy transaction tracked by Renewables.digital (1 as seller) in April 2026, with a combined capacity of 95 MW. Technologies: Battery Storage (BESS) (1). Countries: Finland (1). The most recent deal is “FP Lux European Battery Storage Fund Acquires 95 MW / 220 MWh BESS Project in Alapitkä, Finland” (23 April 2026).
The FP Lux European Battery Storage Fund, advised by re:cap global investors, has acquired a 95 MW / 220 MWh BESS project in Alapitkä, Lapinlahti municipality, Finland, developed by SMA Altenso and Infinergies Finland. SMA Altenso will execute the full EPC contract using grid-forming inverter technology. Construction begins spring 2026 with commissioning planned for H2 2027.
Data as of 30 September 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.