Swift Current Energy appears in 2 renewable energy transactions tracked by Renewables.digital (2 as seller) between January 2026 and March 2026, with a combined capacity of 2,600 MW. Technologies: Battery Storage (BESS) (2) and Solar PV (1). Countries: United States (2). The most recent deal is “Cypress Creek Renewables Acquires 2.45 GW Solar and 720 MW BESS Steel River Project in Arkansas from Swift Current Energy” (11 March 2026).

  • 2Transactions
  • 2,600 MWTotal capacity
  • 1Countries
  • 1With PPA
  • January 2026 – March 2026Period

Key facts

All transactions involving Swift Current Energy

Largest transactions by capacity

Questions & answers

How many transactions involving Swift Current Energy are listed?

Renewables.digital currently lists 2 transactions involving Swift Current Energy between January 2026 and March 2026, with a combined capacity of 2,600 MW.

What has Swift Current Energy acquired?

No acquisitions by Swift Current Energy are currently listed.

What has Swift Current Energy sold?

Cypress Creek Renewables Acquires 2.45 GW Solar and 720 MW BESS Steel River Project in Arkansas from Swift Current Energy (11 March 2026) and Elevate Renewables Acquires 150 MW / 600 MWh Prospect Power BESS Project in Virginia from Swift Current Energy (15 January 2026).

What is the largest of the transactions involving Swift Current Energy?

Cypress Creek Renewables Acquires 2.45 GW Solar and 720 MW BESS Steel River Project in Arkansas from Swift Current Energy with 2,450 MW (11 March 2026).

Deal summaries

Cypress Creek Renewables Acquires 2.45 GW Solar and 720 MW BESS Steel River Project in Arkansas from Swift Current Energy

11 March 2026 · 2,450 MW · United States

Cypress Creek Renewables has acquired the Steel River project from Swift Current Energy, a 2.45 GW solar PV and 720 MW / 2.9 GWh BESS development in Mississippi County, Arkansas. One of the largest solar-plus-storage projects in the United States, Steel River will be built in three phases with total capital costs exceeding $4.5 billion, and all phases are expected to be in service by 2029. The acquisition doubles Cypress Creek's operating and under-construction portfolio to nearly 7 GW.

Counterparties

Countries

Directories

Data as of 13 October 2026. The overview covers the transactions currently listed in the Renewables.digital database; each deal links to its original public source.